New Ferry Regeneration logoNew Ferry Regeneration

Milestones

  • Consultation and masterplan development

    2017

     

    -

     

    2021

    Wirral Borough Council engaged local business and residents during two consultations in 2017 and 2019, to inform of the masterplan and gather feedback to enable an outline planning application to be made. Outline planning permission was granted in September 2020.
  • Preferred developer appointment

    August 2021

     

    -

     

    March 2022

    A competitive tender process was held to appoint a preferred developer(s), who would become a key partner in regenerating New Ferry. The Regenda Group was appointed in March 2022.
  • Design workshops

    April 2022

     

    -

     

    August 2022

    The Project Team have been developing the New Ferry masterplans further, ready to share with local businesses and residents at the community event.
  • Community Event

    22nd September 2022

     

    -

     

    23rd September 2022

    Community Events will be held at Windsor Close Community Centre between 2:30pm - 6pm on 22nd and 23rd September. You will have the opportunity to view the masterplans, share your opinions and speak with representatives from the Project Team.
  • Take part in our survey

    21st September

     

    -

     

    7th October

    Following the community events, the online survey will remain open for comments until 7th October 2022.
  • Final design - Sites B & C

    October 2022

     

    -

     

    November 2022

    The Project Team will finalise the design of Sites B and C and will submit full a planning application in Autumn 2022.
  • Planning Application - Sites B & C

    December 2022

     

    -

     

    December 2022

    Planning application for Sites B & C submitted to Wirral Borough Council
  • Final design - Site A

    October 2022

     

    -

     

    February 2023

    Further design work will continue for Site A before plans are submitted for full planning in around February 2023.
  • Highways and Public Realm work to commence

    2023

     

    -

     

    2024

    Improvements to the highway and public realm on Bebington Road are due to begin.
  • Residential scheme to start on site

    Summer 2023

     

    -

     

    Spring 2026

    We anticipate that development works for Sites B and C will commence in summer 2023 (subject to planning approval). This will be followed by Site A.